Misery Hill, Docklands Dublin
Basement
car park with podium deck requiring a crack bridging waterproof
system.
Project Duration - 24th July - 25th Sept 2002 (installed in 3
phases).
Project Size - 3600m2, 400lm drainage channels.
Project Requirements - Flexible waterproof deck membrane with crack
bridging properties.
Stages - There were 2 Stages
Stage 1 - Surface Preparation
Stage 2 - Spraying Membrane
Materials Used - Fosroc SM, min depth 2mm.