Atlantic Harvest, Fanad Head
New extension to large fish preparation factory in Fanad Head
Donegal. The client required a hard wearing, chemical
resistant and attractive floor, which was had to blend in
with existing floor installed by PFT Systems 6 years ago.
Project Duration - 16th - 20th October 2006
Project Size - 980m2
Existing Conditions - 3 Areas.
Area 1 - Process/Production - 980m2 Epoxy Quartz Screed.
Also 500lm of upstands
Area 2 - Employee Area - 100m2 Decrotaive Flake System.
Stages - There were 4 Stages
Stage 1 - Preparation
Stage 2 - Priming/Surafce DPM
Stage 3 - Laying Floor Screed
Stage 4 - Seal Floor
Materials Used - Resdev Epoxy Screed