Industrial flooring, bund, bund lining, chemical resistant flooring, anti-static flooring, concrete design and installation, airport runway maintenance, joint sealants, waterproof decking systems, waterproofing, basement waterproofing,  surface preparation, floor coatings, anti-slip, finishes, decorative, dustproofing, epoxy, epoxy paint, epoxy resin, epoxy floor coatings, polyurethane, screed and coating specialists copyright©2002 PFT Systems Ltd. all rights reserved.
 
Home Profile Services Projects News
Overview References Images Movies

Print This Page


Hanlon Transport, Dundalk

An existing large storage facility requiring a steel fibre reinforced concrete slab on piles, which achieved FM2 Special category by FACE Consultants

Project Duration -
26th February - 26th February 2004

Project Size -
2200m2 (Completed in 1 day)

Existing Conditions -
Piled ground

Stages -
There were 6 Stages

Stage 1 -
Preparation (Protection of internal finished block work. Setting of levels and fitting isolation material around walls and columns.)
Stage 2 -
Addition of super-plasticiser and steel fibre reinforcement to back off mixing truck. Checking off slump and fibre count/distribution.
Stage 3 -
Placement of concrete using our Somero S240 laser screed.
Stage 4 -
Power trowel concrete and application of spray on acrylic sealer.
Stage 5 -
Saw cutting
Stage 6 - Flatness survey carried out by FACE Consultants - Project achieved FM2 Special Category (to find out more about flatness categories please click here.)

 


*to select another project click here*

Do you like the photographs, then why not view or download the movie of this project by clicking here

Levelling & pouring of concrete

Levelling & pouring of concrete

Close up of our Somero 240

Levelling of concrete

Power trowelling of concrete

Finish view of concrete

Finish view of concrete

Finish view of saw cut concrete

 

:: PFT Systems Ltd : Unit 50-51, Armagh Business Centre, Armagh, BT61 7NH : ph: +44 (0) 2837511122 : fx: +44 (0) 2837511120 ::