Multi story car park requiring an elastic crack bridging
wearing system to the upper decks and to decks at first floor
level over retail shopping units.
Project Duration - 12th Apr - 20th Apr 2003
Project Size - 5500m2
Existing Conditions - New power trowel concrete
Stages - There were 6 Stages
Stage 1 - Preparation
Stage 2 - Priming
Stage 3 - Over banding to cracks and construction
joints
Stage 4 - Apply elastic crack bridging waterproof layer
Stage 5 - Intermediate coating with cast on slip
resistant aggregate
Stage 6 - Top coat and yellow lines