Industrial flooring, bund, bund lining, chemical resistant flooring, anti-static flooring, concrete design and installation, airport runway maintenance, joint sealants, waterproof decking systems, waterproofing, basement waterproofing,  surface preparation, floor coatings, anti-slip, finishes, decorative, dustproofing, epoxy, epoxy paint, epoxy resin, epoxy floor coatings, polyurethane, screed and coating specialists copyright©2002 PFT Systems Ltd. all rights reserved.
 
Home Profile Services Projects News
Overview References Images Movies

Print This Page


Benburb Bramley Apples, Benburb

PFT Systems have recently installed of 6mm deep polyurethane screeds using power troweled techniques, which allows consistency of finish over large areas

Project Requirements - Installation of polyurethane screed to create falls within the floor.  And the supply and installation of additional drainage channels.  Had to resist constant attack of malic acids (apple juice) and allow for easy daily cleaning. 

Project Duration - 12th December 2001 to 23rd December 2001 

Project Size - 660 m2 

Existing Conditions - Install to both new and old concrete. 

Stages - There were 5 Stages

Stage 1 - Preparation
Stage 2 - Priming
Stage 3 - Apply 2nd Coat of Primmer
Stage 4 - Laying Floor Screed
Stage 5 - Apply Top Coat 

Materials Used - Flowcrete HF 

To view Flowcrete's Press Release for Bramley Apples click here


*to select another project click here*

 

Preparation begins on old floor 

Floor laid and power toweled on

Finished floor

Finished floor

Finished floor

Finished floor

Finished floor

Finished floor

 

:: PFT Systems Ltd : Unit 50-51, Armagh Business Centre, Armagh, BT61 7NH : ph: +44 (0) 2837511122 : fx: +44 (0) 2837511120 ::